Grand Parkway:

Contractor(s): TransCore

  • 08/31/2026 – 09/01/2026: SB alternating main lane closures on the Grand Parkway at New Territory. Closures begin at 9:00 pm and end at 5:00 am.
  • 08/31/2026 – 09/01/2026: SB alternating main lane closures on the Grand Parkway at US-90A. Closures begin at 9:00 pm and end at 5:00 am.

Contractor(s): BGE | LJA

  • 08/31/2026 – 09/03/2026: NB/SB alternating frontage road lane closures at Mason Rd and Farmer Rd. Closures start at 9:00 am and end at 3:00 pm. Daily.

Contractor(s): BGE

  • 08/29/2026 – 08/29/2026: NB/SB alternating rolling frontage road lane closures from Canal Rd to Skinner Ln. Closures start at 8:00 am and end at 12:00 pm.

Contractor(s): BGE | Traffic Systems Construction

  • 08/31/2026 – 09/04/2026: NB/SB alternating frontage road lane closures at Peek Rd. Closures start at 9:00 am and end at 3:00 pm. Daily.

Westpark Tollway:

No Scheduled Lane Closures.

Fort Bend Parkway:

No Scheduled Lane Closures.